Page 1 of 1
THE SINGAPORE FLYER
Surveying technology
backing the construction
Sokkia Singapore
Singapore now boasts of
the world's tallest Ferris
wheel, the Singapore
Flyer. It made its first flight in February
2008. UTOC Engineering Pte Ltd used a
SOKKIA NET1200 to overcome the various
challenges associated with the construction
of a world record-setting structure.
The Singapore Flyer occupies a land area
of 33,700 square meters along the Marina
Promenade. Standing at a height of
165 meters, the Singapore Flyer features
28 air-conditioned capsules capable of
holding 27 passengers each. The wheel
has a diameter of 150 meters and one
full rotation will take 37 minutes.
CHALLENGES IN CONSTRUCTION AND THE DECISION TO USE NET1200
The task of constructing the massive
support columns and rim structure
(wheel) was in the hands of the project
managers and engineers from UTOC
Engineering Pte Ltd.
Many challenges surfaced during the
construction, the most pressing of
which were the construction of the
upright support columns within strict
tolerances and the constant monitoring
of the effects of the strong ocean
winds on the rim structure.
Another challenge was presented by
the conditions of the site itself. The
Marina Promenade is a narrow peninsula
of reclaimed land adjacent to the
downtown business district of Singapore.
Limited working space and the
presence of the giant crank station was
a challenge during construction. The tip
of the support structure stands 85
meters high and the cramped work
space required a steep zenith angle to
perform a nearly impossible vertical
measurement.
The solution to this problem started
with a reference to a base line running
across the base of the two support
columns which required both good surveying
technique and a high-precision
total station. The next set of challenges
was presented by the spindle which
forms the axis of the giant Ferris wheel.
The spindle is fitted to both sides of the
support structure and has more than
two thousand bolts, which required
each hole to be measured in relation to
the others before the actual fitting
process began. This required an
extreme amount of patience and a
highly accurate, easy to use instrument
to minimize operator fatigue. The spindle
itself weighs 180 tons and holds 112
radial cables that support the rim structure
and the lifting operation to attach
the spindle was the most critical part of
the entire construction process.
While the engineers were busy fitting
the spindle, the support structure had
to be constantly monitored to ensure
that both ends of the spindle were level
despite differences in lifting speeds of
the four lifting jacks used. This required
an instrument that was both fast and
accurate.
To overcome the challenges in this
high-precision three dimensional structural
project, the construction of the
Singapore Flyer required special attention
to be paid to surveying techniques
and a high performance instrument.
The decision was made to use a SOKKIA
NET1200 3D station. SOKKIA's NET1200
is an ultra-high performance 3D station.
When utilized with SDR4000 3D measurement
software installed on a data
collector, NET1200 can measure and
compare points in three dimensions to
ensure the highest precision.
This system does not require a known
control point as
it can establish a
coordinate system
by measuring
two or three
convenient
points on site.
This allows freedom
of mobility
so engineers can
set up the instrument
at any location
to monitor
the structure.
Using the NET1200, engineers were
able to confidently measure the tip of
the 165 meter tall support rim within
the space constraints of the site. Using
these measurements, the relation to
any point along the support rim or
wheel structure could be easily computed,
greatly reducing working hours
and operator fatigue when monitoring
the entire structure.
SUCCESSFUL CONSTRUCTION STARTS WITH SUCCESSFUL PLANNING
Construction began with the assembly
of the two support structures section by
section. Once the supports were completed,
the spindle was installed.
Installing the spindle was the most
important part of the entire process
and was accomplished after an
exhausting 12-hour operation.
Once the spindle was in place, the segments
of the rim structure were
installed one at a time.
The final stage of the operation was
lifting the capsules to be fitted to the
perimeter of the rim structure.
Throughout the entire operation
SOKKIA reflective sheets were used at
200 points. Working closely with structural
and design engineers, UTOC surveying
engineers pre-planned and
attached reflective sheets to the support
and rim structure components on
the ground before actual construction
began.
Prior to construction, SOKKIA conducted
on-site training for the project
team to simulate the actual working
conditions and made regular visits to
the site and project team.


This was done to ensure that each
member was fully competent in using
the system. During this process,
NET1200 was only sent back once for
general maintenance and cleaning as
required every six months according to
the service contract. Surveyors used
advanced technology to make one of
the most scenic tourist attractions in
the world possible Construction progressed
smoothly and the Singapore
Flyer was completed days ahead of
schedule.
NET1200 successfully accomplished
the task of surveying one of the most
scenic tourist attractions in the world -
The Singapore Flyer.