Conversion contractor selection, management & administration
Robert W. Brown
President & CEO
Baymont Technologies, Inc.
14100 58th Street North
ClearWater, FL 34620
Introduction
Once an organization has decided to implement an AMIFM system and has determined that they
do not have the in-house resources to perform the conversion, they have started down the road to
the selection of a conversion contractor.
At that point, they mayor may not have selected an AM/FM maintenance system (hardware and
software). If a system has already been selected, it mayor may not have been installed. Each of
these scenarios will affect the selection process in a different way. If there is going to be an inhouse
system, the optimum time to take delivery of the first converted work package is at the
same point the operators have become well trained enough to maintain the converted product. If
the user organization has decided not to have a system in-house, it is important to select a
conversion contractor who can provide efficient ongoing maintenance services. If the company
has purchased a software package that requires customization, they may want a conversion
contractor with the expertise to perform the customization.
Selection
Please refer to Figure 1 for a block diagram of the Conversion Contractor Selection Process.
- Education
It is important that the user company have a good understanding of the conversion process before
selecting a conversion contractor. Users can gain this knowledge through the use of one or a
combination of the following methods:
-
Attend technical conferences
- Hire a consultant
- Visit conversion contractors
- Attend conversion seminars
Only with a clear understanding of the complexity of the conversion process can a company
make an informed decision in the choice of a conversion contractor and minimize his reliance on
chance.
In addition to the knowledge to be gained at technical conferences and through the services of a
consultant who has a thorough knowledge of the conversion process, much can be learned by
visiting conversion contractors to observe the process first hand. There are also seminars
available given by conversion contractors or system vendors which cover the conversion subject
in detail.
- Specification
The conversion specification is not an integral part of the conversion contractor selection
process. It is mentioned here because it must be included in any request for proposal but cannot
be properly prepared until after the education phase.
- Pre-qualification
It is impractical to issue a request for proposal (RFP) to a large number of companies. Therefore,
it is important to carefully prepare a short list of companies to which an RFP will be issued.
This pre-qualification process may include one or more of the following:
- Request for Information (RFI)
- Presentations by conversion contractors
- Visits to contractors' offices
- Reference checks
A decision must be made on the number of contractors who will receive the RFP. There maybe
a minimum requirement by the company and the maximum number maybe left open and depend
upon the qualifications of the respondents. Typical short lists contain from three to six company
names.
One method of obtaining a short list is to start from scratch and seek out qualified firms to put on
the list. The most common method, however, is to start with a long list and eliminate the least
qualified. A good source of information for a list of conversion companies is the AM/FM
International Directory. Or even better, consult other organizations in your industry who have
completed conversion projects or currently have them underway.
The request for information (RFI) is a commonly used tool in the pre-qualification process. The
main decisions to be made in the preparation of an RFI are related to the qualifications desired in
a contractor. There are many questions that need to be answered at this time. Answers to
specific questions should be sought in the response to the RFI.
These questions should cover but not be limited to the following subjects:
- key personnel
- in-house equipment
- project experience
- available resources
- company stability
After an initial cut, either instead of or as a result of an RFI, the remaining companies on the list
may be asked to make a presentation either in their own offices or on-site at the user's office.
The advantages of a visit to a contractor's office are obvious. It gives the user exposure to more
of the contractor's employees and business methods. It will also give the contractor a chance to
demonstrate his equipment under actual production conditions. The disadvantage of visiting
several contractors is the travel time and expense involved.
A conversion contractor's references should be thoroughly checked. Each contractor should
provide a contact name and telephone number as reference for each project they have submitted
as similar experience. Conversations with reference contacts should address quality of work,
adherence to schedule, and claims for extra work..
- Request for Proposal
The major step in the contractor selection process is the preparation and issuance of the RFP and
the subsequent evaluation of responses. The content of an RFP will vary depending on several
factors (system selection, contractor pre-qualification, etc.) but it will typically contain the
following sections:
- instructions to bidders
- terms and conditions
- scope of work
- selection criteria
- response format

Figure 1
If there has been no pre-qualification process, then the RFP should also contain all of the
questions normally included in an RFI.
During the preparation of the RFP, certain decisions must be made which will be reflected in the
content. Two very important questions to be answered before the RFP is issued are:
-
What type of contract is desired (lump sum, unit price, time and materials)?
- How will the contractor be selected (low price, qualifications, a formula)?
If a price is requested in the RFP, it should be made clear to those bidding whether it is to be a
firm bid or an estimated price as a basis for negotiation. If it is to be a lump sum bid, then the
scope of work and conversion specifications must be clear, detailed and complete. The bidders
must have access to review all source records and time to determine the quantity of work. In
many cases the user will provide the total quantities (drawing, items of plant, are, etc.) on which
the contractors should base their lump sum bids.
If unit prices are requested, then a review of the source records is important; however, the total
quantities may be estimated with greater tolerance. Time and materials contracts are rare in the
conversion industry and would normally be associated with a not-to-exceed ceiling price.
It is very important that each bidder on the IU?P knows what the user's selection criteria are. If
all bidders have been pre-qualified through an RFI or some other process, then price maybe the
only criterion. Some users may make their selection purely on the technical content of a proposal
and the contractor's qualifications to perform the work. Others may use a formula to select the
successful bidder, assigning weights to each of the selection criteria. It is to everyone's benefit to
spell out the method of contractor selection in the RFP.
In formulating the selection criteria, the company must decide what price should be paid for
quality. If the successful contractor delivers a substandard product or does not meet project due
dates, it could be costly for the user. There maybe people and equipment waiting idle to use the
converted data. Besides the expense, a delay in the project resulting from the poor selection of a
conversion contractor will neither help the career of the project manager nor bolster the
continued support of company management for the AM/FM./GIS project.
To encourage the lowest possible price from each bidder, the user should include the following
items in the RFP: the total amount of future work to be contracted; the schedule for complete
system conversion; and the planned number of contractors to be used on this and any future
contracts.
A response format is an important part of the RFP; it is a standard format which all bidders must
use for their response. It may help to clarify some points in the scope of work to a contractor,
and it will make the task of the evaluators much easier. The response format may include the
following topics:
- proposed prices
- proposed methodology
- conversion team organization chart
- resumes of team members
- project schedule
- assumptions and exceptions
- company qualifications (if no pre-qualification)
- Contract Award
The signing of a contract is the last step in the contractor selection process. It maybe painless or
difficult depending upon how carefully the previous steps in the process have been carried out.
Management
What happens after the selection of a conversion contractor and the execution of a contract?
That depends greatly on the user organization's management of the project's conversion phase.
A typical but simplified project organization chart is shown in Figure 2.
- Proiect Team
The user organization will have a project manager and a project team established before the
conversion contract is awarded. The contractor has agreed to establish a conversion project team
and has included an organizational chart in its proposal. It is essential to the project that the
conversion project team become an integral part of the overall AMlFM7GIS project team. To
achieve this, user and contractor team members must work toward a common goal and establish
communication lines at various levels in the organizational structure.
The main duty of the overall project manager with respect to the contractor is to ensure that a
product of acceptable quality is delivered on schedule. The project manager will have little
control over this if the selection process failed to provide a competent contractor.

Figure 2
The conversion schedule is of utmost importance to the overall AM/FM/GIS project. The project
manager has to schedule his people to do acceptance testing and subsequent maintenance functions on
converted work packages. Assuming that the user has selected a competent contractor, it is important for
the user project team members to remove any roadblocks or bottlenecks that my prevent the conversion
contractor from delivering on time. The basis of these problems is usually a lack of some type of
information on the part of the contractor. To keep the conversion process on track, the conversion team
must receive information in a timely manner.
- Quality Control
By virtue of contracting the conversion to an outside firm, the user's project manager has relinquished the
quality control fiction during the conversion of any one work package (ie. one telephone exchange). He
may return a package for rework if it does not pass the acceptance tests, but checking the quality of the
work on a half completed package cannot be considered. This is because the cost-efficient processes used
by most conversion contractors do not produce a product to review until the end of the process. If the
user's acceptance criteria have been detailed and the conversion specification is well understood, then the
contractor should have no problem in delivering a product which will pass the acceptance testing.
- Communication
There are three main lines of communication necessary between the user's members and the contractor's
members of the project team: project manager to project manager; computer operator to computer operator;
and records technician to records technician. A situation where either project manager says "all
communication must go through me" will be detrimental to the successful execution of the conversion.
The disadvantage of more than one line of communication between two companies is the potential for lack
of control by one of the two project managers. A written report of all telephone conversations copied to
the project manager will avert such problems.
- Penalties
What penalty can be imposed on a contractor who does not meet his contractual obligations? Financial
penalty clauses for failure to meet schedule or quality should be avoided. Penalty clauses will tend to
introduce unwanted tension between the contracting parties. They will also increase bid prices due to the
additional financial risk involved and the certainty of higher administration costs to complete
documentation required for each minor schedule delay. A suggested method for including a penalty clause
is to offset it by adding a bonus clause to reward the contractor for any early deliveries.
The future well-being of any contractor depends on his reputation. This reputation is certainly not
enhanced by producing inferior quality work behind schedule. If a conversion project is behind schedule or
if it must be returned for rework, it is highly possible that the contractor has already accrued financial
penalties without others being added.
If a contractor consistently fails to meet his contractual obligations, then the contract should be canceled
and no further work awarded to him.
Administration
The management of any project requires a certain number of administrative duties. The secret of a
successful project is to find the right balance of administration time. There is a minimum requirement
without which the project will not proceed, and at the other end of the scale there is a theoretical limit
which will completely bog down the project manager with paper work. The optimum amount of
administration will allow for the sound management of a project without spending excessive time on paper
work.
- Communication Methods
Good communication has been discussed as a management tool. The methods used and the recording of
this communication are project administrative functions.
The telephone should be used as the primary communication link between the user and the contractor.
Frequent telephone conversations are the best way to maintain a good working relationship between the
parties. All project related information discussed in a telephone conversation should be recorded in
writing and distributed in a standard project distribution.
The frequency of project meetings will depend on the distance between the offices of the contractor and
user and on contractual conditions. Certainly a kick-off meeting at the beginning of a conversion contract
is recommended to introduce team members to their counterparts and to discuss project specifications and
procedures. Too many intercompany project meetings can be nonproductive.
Written communication between the two parties is essential, especially for dealing with contractual matters
and for transmitting paper documents or computer tapes. The facsimile has become a common mode of
communication between contractor and user. It is especially convenient for solving problems discovered
on the source records.
- Progress Reports
Progress reports are an administrative tool that will help the user project manager keep abreast of the
project schedule. The project report frequency should be determined before signing a contract while a
mutually acceptable format may be decided upon before the start of actual work on the project. A typical
progress report would report the percent complete of each task on each work package that the contractor
has received. The report should be concise and received by the user within a few days of the end of the
reporting period.
- Invoices
The method of invoicing should be spelled out clearly in the contract. Typically on conversion projects
there is monthly invoicing with an amount held back until final acceptance of a converted package. The
amount invoiced may or may not be supported by progress reports depending on the requirements of a
contract. Invoices should be processed and paid within the time specified to help the contractor offset his
high labor costs at the beginning of the conversion period.
- Extra Work
The amount of work performed beyond the scope defined in the contract will depend on the completeness
of the conversion specification and the number of unlmowns at the time of the contract signing. Excessive
extra work will cause hard feelings between the parties and should be avoided. The user project manager
should try to anticipate the quality of extra work on a project by making himself aware of the gray areas of
the specification - those which cannot be adequately defined prior to starting work.
A good rule of thumb is - the lower the contract price in comparison to other bids, the more claims for
extras there will be. Often the idea of extra work is not mentioned in a contract using an "out of sight - out
of mind" philosophy. The rules for claiming, documenting and paying for extra work should be detailed in
the contract in order to avoid problems at a later date.
Conclusion
There are many things to consider before entering into a contract for the conversion of records to an
AM/FM/GIS system. With a capable project team, a thorough knowledge of the conversion phase of a
project, and a well-thought-out selection process, a user organization should have few problems in contract
management and administration. The selection of a qualified contractor is the most important step in the
conversion phase and it should not be left to chance.
|