Logo GISdevelopment.net

GISdevelopment > Proceedings > GITA > 2001


GITA 2002 | GITA 2001 | GITA 2000 | GITA 1999 | GITA 1998 | GITA 1997 |  
Sessions

A tangled web of pure opportunity

Directions for data

Forging the future

How they did it - and what's next

Integrating work management

Mobile solutions- taking it to the streets

Operations support

People make the difference

Systems architecture

The local government perspective

Tying IT all together

Vertical applications


GITA 2001


How They Did It - And What's Next


Using GIS for tax asset allocation


Old System
The old system consisted of communicating throughout the years on all new projects files from Engineering, determining the total cost for the project, and communicating this to Plant Accounting by reporting such items as size, type, length, and date of installation of pipe, and determining these amounts within each tax district. In addition, other departments reported assets to Plant Accounting such as station costs by project file, building and land costs by tax district, and inventory by address. Plant Accounting also maintained a running total of costs for such assets as meters, service mains, and right of ways, not knowing what tax district they actually existed in.

When new projects replaced old projects, it was Engineering's responsibility to report to Plant Accounting the size, type, date installed, and length of pipe that was retired for each tax district. Plant Accounting would then try and update FLAME based on these numbers. When new tax districts were created or boundaries were changed, Engineering would have to determine lengths of pipe by size, type, and date installed that needed to be moved from one tax district to another. This process went on all year, year after year. Then, by February of the following year, the costs would need to be added up based on new tax district boundaries and reported to the state. If there were large changes in asset costs for a specific tax district, explanations in the form of legal documents would need to be submitted to the State of North Carolina. This tedious and stressful process, which was performed by a number of departments throughout the year(s), often was put off until the last moment, and breakdown in communications often occurred.

Recommendations
It was agreed upon that FLAME and TIGER would supply the necessary dataflows into a Microsoft Access Database in order to prepare the annual reports. The Figure below shows what data was used from each system. There are five defined methods of allocating costs by tax district. Based on the geographic information maintained in TIGER and the level of detail costs maintained in FLAME, one of the five methods was selected to allocate costs. Following is an example of each of the five methods of allocation

Method 1. Allocation based on a single point feature in TIGER
In the following illustration, FLAME reported the project cost for project number A100 was $40,000.00. TIGER was able to locate a Station which has the project number as an attribute and determined it to be in Tax District 100. Thus, the $40,000.00 was allocated to Tax District 100. This was the simplest and most straightforward allocation method.



Method 2. Allocation based on a Tax District
For certain features that did not exist in TIGER, FLAME was able to provide the cost and the tax district and this data was loaded into the database. Many buildings and land fit into this allocation method.

Method 3. Allocation based on a specific Linear Feature
Using method 3, a linear feature such as a Transmission Pipe crossed many tax districts. FLAME was able to provide a total cost for the installation of the Transmission Main based on the Transmission Line Number. TIGER was able to determine what percentage of the pipe length existed in each tax district. The total cost from FLAME was then multiplied times the percentage of pipe length in each tax district to determine the allocation cost.



Method 4. Allocation based on many linear features
In the next example, many linear features were used to allocate costs based on a category. FLAME was able to provide the total cost for Distribution Main based on a combination category of size, type (material), and year installed. TIGER then determined the total length of pipe for each category of size, type, and year. It then determined the percentage that existed in each tax district. The total cost for each category of Distribution Main was then multiplied by each percentage of that category in each tax district to determine the allocation cost.

Page 2 of 3
| Previous | Next |

Applications | Technology | Policy | History | News | Tenders | Events | Interviews | Career | Companies | Country Pages | Books | Publications | Education | Glossary | Tutorials | Downloads | Site Map | Subscribe | GIS@development Magazine | Updates | Guest Book