Outage management system helps keep the lights on in east texas
Data residing in a geodatabase cannot be used in an OMS. The data needs to be
converted to format that can be used by the OMS. MJH wrote the software to perform
this conversion. Not only does the software convert the data, but it also creates an error
file that reports any problems that might exist in the data. Each feeder will have to be
converted, edited for any errors and reconverted before the data can be inserted into the
OMS.
Production Phase
Due to a large backlog of work orders and the need to have a service to transformer
connection, a decision was made to perform a full field survey of SHECO’s entire
system. To save time in the survey work and maintain important attribute information,
existing data that resided in the geodatabase would be exported out to the GPS units and
taken out into the field for verification.
Upon approving a means of creating accurate data, we began the survey data collection
phase of the project. Immediately, we ran across some hardware performance issues.
The intent was to load all of the data for one feeder into a GPS device to take out into the
field for data collection and verification. Using the current devices, we could only get
about 25% of the data for an average feeder on the devices. This required us to either
split up the data within a feeder or upgrade the GPS device to something with larger
processing and memory capabilities. An attempt to split up the data proved to be very
time consuming and confusing to the survey crews, so the hardware was upgraded to
allow more data to be stored.
After a few days to get the survey procedures set, we were ready to start a large field
survey effort. Approximately 15, one man, survey crews were assembled. Each one
provided with the necessary equipment to efficiently collect and verify the field data.
The area that we were dealing with is mostly rural and forested. This created some
unusual situations. Each survey crew was equipped with an ATV. This allowed for easy
passage on questionable roads and also allowed the surveyor to collect and verify much
of the data without ever having to get out and walk. Another unusual situation was the
large number of aggressive dogs that surveyors had to deal with. For this, each person
was given dog repellant spray. Other problems that were encountered included locked
gates and unhappy residents. Eventually all these issues were overcome and the data
made it to the quality control phase of this job.
Once the data made it into the office, each feature shapefile was thoroughly examined. If
any data was missing, incomplete or inaccurate, the surveyor would be sent back into the
field to recollect it. Once SHECO was satisfied with the data, it would be sent to MJH
for more quality control and eventually be loaded back into the database. The data would
be looked at three times before it would be loaded into the database. A project manager
that oversaw the day to day operations of the survey crews would make sure the data was
complete and accurate. Then the data would be sent to SHECO where a GIS analyst
would open up the attribute tables and make sure that everything was valid. SHECO
would also randomly check some of the data in the field to ensure that the survey crews
were collecting the data correctly. Once SHECO was through with their checks, it would
be sent to a project manager at MJH. There the data would be put through a series of
checks that included connectivity, attribute and visual accuracy. If errors were
encountered that couldn’t be resolved over e-mail or the telephone, the data would then
be sent back to the project manager of the survey crew for corrections.
After several feeders were done with the collection, verification and quality control
checks, a geodatabase load would be performed by MJH. The decision was made to
input around 10 to 20 feeders at a time. The time it takes to perform the geodatabase load
is usually the same whether you did one feeder or twenty feeders at a time. So a large
number of feeders would be prepared and then loaded in at one time instead of loading
each one individually. The process was to first load all the shapefile data to a personal
geodatabase, create the units tables with a bank tag relationship then load the personal
geodatabase and unit tables to the SDE geodatabase.
OMS Insertion Phase
The data that has been collected, verified and been through endless quality control work
still is not ready for the OMS. Software written by MJH needs to be run on each feeder
to perform the conversion and error reporting. The error file that is created will find
problems that will prevent the OMS from working properly. Incorrect phasing and
disconnected features would be common errors that show up in the error file. All valid
errors need to be corrected before the converted data can be inserted into OMS. This
phase of the project was performed by SHECO. The error files contained x and y
coordinates that allowed the user to find the exact location of the problem. This process
was further simplified by creating an error shapefile from the coordinates. The shapefile
could then be used to locate and fix the problems. Once all of the errors are corrected for
a feeder, it can be loaded into the OMS.
Conclusion
This project proved to be challenging for all of those involved. The success hinged on
planning and tireless efforts by all. Many steps were taken to go from an idea to an
operational OMS. During the way, many problems were encountered and eventually
solved. This was a learning experience for all of those who took part in this large
undertaking. The result of this effort is an effective tool to deal with electrical outages,
which will not only result in a more efficient electrical cooperative, but more satisfied
customers.